LEGGI IL QUOTIDIANO
LEGGI IL QUOTIDIANOOggi 11 November
L'Unione Sarda English
Abbonati
ITA|ENG|DEU|RUS|CIN
videolina Linkradiolina linkSardegna 1 linkVai online linkPBM link
Read the newspaper
L'Unione Sarda English
Subscribe
L'Unione Sarda

Iniziative Editoriali

  • Biblioteca dell'identità

Account

  • Abbonati
  • LEGGI IL QUOTIDIANO
ABBONATI A L’UNIONE SARDA

SCARICA L'APP L'UNIONE DIGITAL

Download GoogleDownload apple
videolina Linkradiolina linkVai online linkPBM link

2021 L'Unione Sarda S.p.A. Tutti i diritti riservati. É vietata la riproduzione, anche parziale e con qualsiasi mezzo, di tutti i materiali del sito. | Indirizzo della Sede Legale: Piazzetta L'Unione Sarda nr. 24 | Capitale sociale 11.400.000,00 i.v. | Codice Fiscale ed iscrizione presso l'Ufficio Registro Imprese di Cagliari 01687830925 (P.I. 02544190925) | REA: CA-136248

Cookie e Privacy PolicyModifica impostazioni privacyInformativa commentiCorporate
L'Unione Sarda

News

  • Cronaca Sardegna
  • Economia
  • Salute
  • Cultura
  • Sport
  • Gossip
  • Turismo

Servizi

  • Necrologi
  • Annunci
  • Pubblicità

Bella Sardegna

  • Spiagge

Iniziative Editoriali

  • Biblioteca dell'identità

Account

  • Abbonati
  • LEGGI IL QUOTIDIANO
ABBONATI A L’UNIONE SARDA

SCARICA L'APP L'UNIONE DIGITAL

Download GoogleDownload apple
videolina Linkradiolina linkVai online linkPBM link

2021 L'Unione Sarda S.p.A. Tutti i diritti riservati. É vietata la riproduzione, anche parziale e con qualsiasi mezzo, di tutti i materiali del sito. | Indirizzo della Sede Legale: Piazzetta L'Unione Sarda nr. 24 | Capitale sociale 11.400.000,00 i.v. | Codice Fiscale ed iscrizione presso l'Ufficio Registro Imprese di Cagliari 01687830925 (P.I. 02544190925) | REA: CA-136248

Cookie e Privacy PolicyModifica impostazioni privacyInformativa commentiCorporate
HomeSardinia
social housing

Cagliari, 10 years for a concrete skeleton: construction site for low-cost housing in San Benedetto has been unblocked.

Construction time has increased almost three times over expected. The municipality and the contractor reached an agreement: compensation has been awarded, and a new firm is now being sought to complete the 40 apartments between Via Boito, Via Donizetti, and Via Rossini.
Ennio Neri
26 settembre 2026 alle 09:54
Cagliari, 10 years for a concrete skeleton: construction site for low-cost housing in San Benedetto has been unblocked.
Il cantiere tra via Boito, via Donizetti e via Rossini
Resta informato su WhatsApp
FacebookXLinkedInWhatsApp
Argomenti similiSLOT_5
  • Russi e russanti
    Caffè Scorretto

    Russi e russanti

    Luigi Almiento

Articoli correlati

Grillo's appeal, the defense: "Evidence in our favor was ignored or undervalued, the trial must be retried."
Sassari

Grillo's appeal, the defense: "Evidence in our favor was ignored or undervalued, the trial must be retried."

In the grounds of appeal, a flurry of objections raised by the lawyers to the regularity of the conviction sentence of the Tempio Tribunal
Andrea Busia
Girasole: Mosquitoes test positive for the Usutu virus: Mayor's order comes into effect.
the alarm

Girasole: Mosquitoes test positive for the Usutu virus: Mayor's order comes into effect.

The verdict from the Teramo zooprophylactic institute is the first case in the municipality.
Roberto Secci
Bomb scare, schools aren't closing. Meloni: "They want to scare us, not hit us. We'll react."
the emergency

Bomb scare, schools aren't closing. Meloni: "They want to scare us, not hit us. We'll react."

The prime minister called on the opposition and reassured them in a video on social media: "Nothing was found in the institutions. Those who send these threats want a nation that is terrified and fea…
Costa Smeralda, the "emery gang" and thefts from dream villas: crimes prescribed after 16 years
Olbia

Costa Smeralda, the "emery gang" and thefts from dream villas: crimes prescribed after 16 years

In 2010, raids took place in Porto Cervo and Olbia, with the villa of an undersecretary of Labour and the residence of a Roman countess also targeted.
Andrea Busia
Ciro Grillo trial: appeal faces immediate risk of postponement
court

Ciro Grillo trial: appeal faces immediate risk of postponement

The defense: "A judge's signature is missing; the first-instance ruling must be retried."
Cabras, the Casula family's historic supermarket is closing: "We can't keep going."
in the center

Cabras, the Casula family's historic supermarket is closing: "We can't keep going."

In Corso Umberto, the shutters will be lowered after 80 years of activity.
Sara Pinna
Sassari: Drunk man hits nurse in ER lip
the violence

Sassari: Drunk man hits nurse in ER lip

The man was arrested by the Carabinieri, and the victim was given ten days of treatment.
Emanuele Floris
Quartu, workshops and guided tours dedicated to tradition
the event

Quartu, workshops and guided tours dedicated to tradition

The “Tramudas” festival, organised by the Sa Cobula association with the natural shopping centre, makes its debut on Thursday
Georgia Daga
The book "Walking in Silence" will be presented in Nuoro.
The meeting

The book "Walking in Silence" will be presented in Nuoro.

The volume edited by researcher Mariella Napolitano will be presented on Friday

Changes, delays, rising material prices, and intermittent construction, partly due to the heat. A long story spanning nearly ten years has reached its final chapter. But not with the inauguration of the homes, but with a "consensual divorce." The issue of the low-cost housing planned for Via Boito, Via Rossini, and Via Donizetti has been resolved . The Municipality of Cagliari and the company "Costruzioni Mariano Cabras" have signed an early termination of the contract for the social housing project in San Benedetto, which involves the demolition of an old municipal building and the construction of 40 new affordable rental units. The agreement prevents the construction site from being held up for years in court.

Established way back in 2007 through a program agreement between the Region and the Municipality and reorganized in 2015 with European funding totaling over €4.5 million, the project was awarded to the Cabras company in 2015 for approximately €3 million . However, since work began in 2018, the construction site has become an obstacle course : five variant and supplementary appraisals, additional technical studies for safe demolition, unexpected disruptions to public utility networks, and then the summer heatwaves. All of this has increased the theoretical duration of the work from the initially planned 540 days to 1,368 days. The crucial point comes in 2025: with the severe delay, the contractual penalties payable by the company had exceeded the maximum threshold of 10% (equal to over €397,000). On the other hand, the construction company has complained about the financial imbalance caused by the rising prices of raw materials.

Faced with the real risk of a lengthy and costly lawsuit, the municipal administration, having received a favorable opinion from the legal team, decided to seek a settlement . In the end , Palazzo Bacaredda will award the company compensation of approximately €270,000 . The demolition of the old building has been completed, and the entire rough frame of the new building (foundations, pillars, floors, and elevator shafts) has been constructed. All that remains is the infill walls, the systems and interior finishes, and finally the landscaping of the outdoor area and the connections to public utilities. Now the ball is back in the court of the technical offices on Via Roma: to complete the 40 apartments, the Municipality will have to issue a new tender to assign the work and then deliver the apartments to the families struggling with the housing emergency.