LEGGI IL QUOTIDIANO
LEGGI IL QUOTIDIANOOggi 12 November
L'Unione Sarda English
Abbonati
ITA|ENG|DEU|RUS|CIN
videolina Linkradiolina linkSardegna 1 linkVai online linkPBM link
Read the newspaper
L'Unione Sarda English
Subscribe
L'Unione Sarda

Iniziative Editoriali

  • Biblioteca dell'identità

Account

  • Abbonati
  • LEGGI IL QUOTIDIANO
ABBONATI A L’UNIONE SARDA

SCARICA L'APP L'UNIONE DIGITAL

Download GoogleDownload apple
videolina Linkradiolina linkVai online linkPBM link

2021 L'Unione Sarda S.p.A. Tutti i diritti riservati. É vietata la riproduzione, anche parziale e con qualsiasi mezzo, di tutti i materiali del sito. | Indirizzo della Sede Legale: Piazzetta L'Unione Sarda nr. 24 | Capitale sociale 11.400.000,00 i.v. | Codice Fiscale ed iscrizione presso l'Ufficio Registro Imprese di Cagliari 01687830925 (P.I. 02544190925) | REA: CA-136248

Cookie e Privacy PolicyModifica impostazioni privacyInformativa commentiCorporate
L'Unione Sarda

News

  • Cronaca Sardegna
  • Economia
  • Salute
  • Cultura
  • Sport
  • Gossip
  • Turismo

Servizi

  • Necrologi
  • Annunci
  • Pubblicità

Bella Sardegna

  • Spiagge

Iniziative Editoriali

  • Biblioteca dell'identità

Account

  • Abbonati
  • LEGGI IL QUOTIDIANO
ABBONATI A L’UNIONE SARDA

SCARICA L'APP L'UNIONE DIGITAL

Download GoogleDownload apple
videolina Linkradiolina linkVai online linkPBM link

2021 L'Unione Sarda S.p.A. Tutti i diritti riservati. É vietata la riproduzione, anche parziale e con qualsiasi mezzo, di tutti i materiali del sito. | Indirizzo della Sede Legale: Piazzetta L'Unione Sarda nr. 24 | Capitale sociale 11.400.000,00 i.v. | Codice Fiscale ed iscrizione presso l'Ufficio Registro Imprese di Cagliari 01687830925 (P.I. 02544190925) | REA: CA-136248

Cookie e Privacy PolicyModifica impostazioni privacyInformativa commentiCorporate
HomeSardinia
Cagliari

Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."

Arnas management responds to the unions, who have complained about denied care: "No patient left behind." Meanwhile, yet another announcement regarding the completion of the operation arrives: "Spring 2027." The June and December 2026 dates have been postponed.
Enrico Fresu
1 novembre 2026 alle 15:26
Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."
The construction site of the Businco operating rooms
Resta informato su WhatsApp
FacebookXLinkedInWhatsApp
Argomenti similiSLOT_2
  • Da che parte sta?
    Caffè Scorretto

    Da che parte sta?

    Tacitus

Articoli correlati

Grillo's appeal, the defense: "Evidence in our favor was ignored or undervalued, the trial must be retried."
Sassari

Grillo's appeal, the defense: "Evidence in our favor was ignored or undervalued, the trial must be retried."

In the grounds of appeal, a flurry of objections raised by the lawyers to the regularity of the conviction sentence of the Tempio Tribunal
Andrea Busia
Girasole: Mosquitoes test positive for the Usutu virus: Mayor's order comes into effect.
the alarm

Girasole: Mosquitoes test positive for the Usutu virus: Mayor's order comes into effect.

The verdict from the Teramo zooprophylactic institute is the first case in the municipality.
Roberto Secci
Bomb scare, schools aren't closing. Meloni: "They want to scare us, not hit us. We'll react."
the emergency

Bomb scare, schools aren't closing. Meloni: "They want to scare us, not hit us. We'll react."

The prime minister called on the opposition and reassured them in a video on social media: "Nothing was found in the institutions. Those who send these threats want a nation that is terrified and fea…
Costa Smeralda, the "emery gang" and thefts from dream villas: crimes prescribed after 16 years
Olbia

Costa Smeralda, the "emery gang" and thefts from dream villas: crimes prescribed after 16 years

In 2010, raids took place in Porto Cervo and Olbia, with the villa of an undersecretary of Labour and the residence of a Roman countess also targeted.
Andrea Busia
Ciro Grillo trial: appeal faces immediate risk of postponement
court

Ciro Grillo trial: appeal faces immediate risk of postponement

The defense: "A judge's signature is missing; the first-instance ruling must be retried."
Cabras, the Casula family's historic supermarket is closing: "We can't keep going."
in the center

Cabras, the Casula family's historic supermarket is closing: "We can't keep going."

In Corso Umberto, the shutters will be lowered after 80 years of activity.
Sara Pinna
Sassari: Drunk man hits nurse in ER lip
the violence

Sassari: Drunk man hits nurse in ER lip

The man was arrested by the Carabinieri, and the victim was given ten days of treatment.
Emanuele Floris
Quartu, workshops and guided tours dedicated to tradition
the event

Quartu, workshops and guided tours dedicated to tradition

The “Tramudas” festival, organised by the Sa Cobula association with the natural shopping centre, makes its debut on Thursday
Georgia Daga
The book "Walking in Silence" will be presented in Nuoro.
The meeting

The book "Walking in Silence" will be presented in Nuoro.

The volume edited by researcher Mariella Napolitano will be presented on Friday

The delays in the construction of the Businco operating rooms? Blame it on "the extremely high technical and technological complexity of the interventions, and on the intense heat of last summer, which, in compliance with legal provisions, forced construction work to be suspended at 12:00 PM." These, according to a press release from Brotzu, are the reasons for the delay in the completion of the operating block at Cagliari's Oncology Hospital.

Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."

The initial goal "under the NRRP funding was to complete the earthquake-resistant work (the load-bearing structure) by June," ARNAs said. However, due to the complexity and heat, "an extension was granted until August 10th. This extension allowed the goal to be achieved and the NRRP funding to be secured."

Sale operatorie cantiere al Businco: «Cure negate ai sardi, non solo un lavoro in ritardo»
la denuncia

Sale operatorie cantiere al Businco: «Cure negate ai sardi, non solo un lavoro in ritardo»

Enrico Fresu

The health authority is thus responding to the attack by the unions (CGIL, FIALS, and CISL), who yesterday, in addition to criticizing the construction site's slow pace, also highlighted the drop in the number of cancer patients transferred to the San Michele hospital (known to everyone as the Brotzu).

Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."

General Manager Maurizio Marcias deflects the controversy: "During the renovations, clinical and surgical activities continued, including gynecological and thoracic surgery at the San Michele hospital," he assures. "All patients were regularly cared for, and the necessary clinical and healthcare services were guaranteed, ensuring the continuity and quality of care."

No patient, Brotzu says, without referring to the numbers provided by trade unionists, "has been left behind and all necessary healthcare services have been provided, ensuring adequate responses."

Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."

But when will the operating rooms be ready? Arnas is stating: "Completion is scheduled for spring 2027."

Last May, the same health authority wrote: "According to the timetable (...) the installation of the high-tech systems and equipment for the new operating rooms must be completed by December 2026. The consortium of companies involved in the project and the design team had to address critical issues related to the complexity of the existing underground structures and the need to operate in maximum safety conditions, elements that inevitably led to an extension of the preliminary activities." So the heat had nothing to do with it.

Operating rooms at the Businco construction site, Brotzu: "The delays? Blame the heat and complex work."

In June 2025, Brotzu was still talking. A statement from Arnas Brotzu read: "The investment," it said, "will allow for the modernization and expansion of the current operating block. Block F, currently equipped with two rooms, "will be completely renovated to accommodate four state-of-the-art integrated video operating rooms, equipped with cutting-edge technology that represent the most modern operating rooms in the regional healthcare system, with adequate support spaces to ensure maximum efficiency and safety in surgical procedures." The project is expected to last approximately thirteen months "and will be completed by June 2026."